Feds Add $201M for CA High-Speed Rail Projects in Kern County

Published

on

In May, Builders finished the Cedar Viaduct crossing in Fresno that would bring high-speed rail trains over Highway 99. (High-Speed Rail Authority)
Share with friends

California’s high-speed rail project just got a $201 million boost from the federal government to move the Kern County leg of the journey along.

Official U.S. House portrait of Rep. Jim Costa

“I’m proud to have worked with our federal and state partners to secure this grant to advance this project.” — Rep. Jim Costa, D-Fresno

“This federal grant reflects a commitment from the Biden-Harris Administration to bringing modern transportation into the 21st century starting here in California’s San Joaquin Valley,” said Rep. Jim Costa (D-Fresno) in a statement. “I’m proud to have worked with our federal and state partners to secure this grant to advance this project.”

The money will go toward designing and purchasing right-of-ways in Shafter. The six grade separations will help buffer car and pedestrian traffic from both freight trains and high-speed rail trains, according to a news release from Costa’s office.

The money came from the infrastructure law passed in November 2021 — more specifically, the 2022 Consolidated Rail Infrastructure and Safety Improvements Program.

California High-Speed Rail Authority CEO Brian Kelly said in a statement he expects the southern end of the rail line to soon be finished.

“With the southernmost 22-mile stretch of active construction due to be complete this fall, this latest federal commitment represents a major step forward in our effort to deliver passenger service in California,” Kelly said. “We look forward to this continued partnership with the Biden-Harris Administration.”

Seven Structures, 90 Miles Completed

In 2019, Gov. Gavin Newsom scaled back the rail project to 119 construction miles between Merced and Bakersfield. Of that stretch, 90 miles of guideway have been completed, according to the May report from the California High-Speed Rail Authority. Another 52 miles of extensions are planned to connect downtown Bakersfield and downtown Merced.

Seven structures have been completed in 2023, including the Cedar Viaduct in Fresno that crosses Highway 99.

In August, the rail authority began the bidding process for the trains themselves.

Planners hope to have the first trains running by 2030. Analysts peg the cost to finish the Central Valley segment at $35 billion, $10 billion more than funding levels, according to CalMatters reporter Ralph Vartabedian.

The most recent cost estimate for the 500 miles between San Francisco and L.A. would leave a funding gap of $100 billion, according to Vartabedian.

Edward Smith began reporting for GV Wire in May 2023. His reporting career began at Fresno City College, graduating with an associate degree in journalism. After leaving school he spent the next six years with The Business Journal, doing research for the publication as well as covering the restaurant industry. Soon after, he took on real estate and agriculture beats, winning multiple awards at the local, state and national level. You can contact Edward at 559-440-8372 or at Edward.Smith@gvwire.com.